Stalled by pandemic, MRT Line-1 gets time extension
Skip to main content
  • Home
  • Economy
    • Aviation
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • World+Biz
  • Sports
  • Features
    • Book Review
    • Brands
    • Earth
    • Explorer
    • Fact Check
    • Family
    • Food
    • Game Reviews
    • Good Practices
    • Habitat
    • Humour
    • In Focus
    • Luxury
    • Mode
    • Panorama
    • Pursuit
    • Wealth
    • Wellbeing
    • Wheels
  • Epaper
  • More
    • Subscribe
    • Videos
    • Thoughts
    • Splash
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • COVID-19
    • Games
    • Long Read
    • Interviews
    • Offbeat
    • Podcast
    • Quiz
    • Tech
    • Trial By Trivia
    • Magazine
  • বাংলা
The Business Standard

Friday
January 27, 2023

Sign In
Subscribe
  • Home
  • Economy
    • Aviation
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • World+Biz
  • Sports
  • Features
    • Book Review
    • Brands
    • Earth
    • Explorer
    • Fact Check
    • Family
    • Food
    • Game Reviews
    • Good Practices
    • Habitat
    • Humour
    • In Focus
    • Luxury
    • Mode
    • Panorama
    • Pursuit
    • Wealth
    • Wellbeing
    • Wheels
  • Epaper
  • More
    • Subscribe
    • Videos
    • Thoughts
    • Splash
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • COVID-19
    • Games
    • Long Read
    • Interviews
    • Offbeat
    • Podcast
    • Quiz
    • Tech
    • Trial By Trivia
    • Magazine
  • বাংলা
FRIDAY, JANUARY 27, 2023
Stalled by pandemic, MRT Line-1 gets time extension

Transport

Jahidul Islam
23 March, 2021, 12:45 pm
Last modified: 23 March, 2021, 01:52 pm

Related News

  • PM to unveil 25 dev projects in Rajshahi on Sunday
  • More than 50% Japan-funded projects lagging behind
  • Brac Bank gets $100m green finance facility from Jica, Citi NA
  • Hundreds take their first metro rides as Tk2.74 lakh earned in fare on first day
  • Japanese tech to raise Dhaka airport's ground handling capacity

Stalled by pandemic, MRT Line-1 gets time extension

Jica extended deadlines for the preliminary activities of the project and called for speeding up the work immediately in order to prevent further delays

Jahidul Islam
23 March, 2021, 12:45 pm
Last modified: 23 March, 2021, 01:52 pm
Stalled by pandemic, MRT Line-1 gets time extension

The 31.24-km Mass Rapid Transit (MRT) Line-1 is yet to see the start of construction, even though the project secured approval in October 2019. 

At a recent appraisal mission meeting, the project financier, Japan International Cooperation Agency (Jica), extended deadlines for the preliminary activities of the project and called for speeding up the work immediately in order to prevent further delays. 

Dhaka Mass Transit Company Ltd (DMTCL), the implementing agency of the project, held the novel coronavirus pandemic responsible for the delay and therefore proposed extending the deadline for pre-construction activities, such as basic and detailed design,preparation of tender document and land acquisition, which the lender later agreed upon. 

In the first phase, an agreement was penned involving a Tk3,895 crore loan from Jica. In the second phase, the appraisal mission meeting was held between Jica and the Bangladesh government to discuss the terms and conditions of the loan. 

The MRT Line-1 project primarily constitutes two routes – one connecting Hazrat Shahjalal International airport with Kamalapur and the other connecting Purbachal with Notun Bazar.

Although the primary designs for the 19.87-km underground metro rail (Airport to Kamalapur) and 11.37-km elevated metro rail (Purbachal to Notun Bazar) have been completed, the details are still in the works. 

The project cost is estimated at Tk52,562 crore. Of this, the government will provide Tk13,111 crore and Jica will loan the remaining Tk39,451 crore. 

At the appraisal mission meeting, Jica stressed the significance of maintaining the project's schedule. It noted that failing to do so might result in delayed loans from Japan. 

The lender also laid stress on the application of advanced technology to ensure quality infrastructure.

Holding the coronavirus pandemic responsible for the delay in starting work on the project, officials of the Dhaka Mass Transit Company Limited (DMTCL) told the meeting that foreign consultants working under the project had left Bangladesh in April 2020 due to the outbreak of Covid-19. 

"Even though they continued working from home on a limited scale, it was difficult to deliver according to the original schedule, which was agreed upon in 2018."

When asked about the delay in MRT projects, Mohammad Nazrul Islam, secretary of the Road Transport and Highways Division, told The Business Standard these kinds of projects required large-scale surveys. 

He added that it was only after the completion of primary preparatory work that the project work at the ground level should commence. 

"The project stalled because of the coronavirus pandemic-induced shutdown enforced by the government and the absence of foreign involvement. 

"The coronavirus proved to be an enormous difficulty to navigate, which hindered and slowed down all kinds of development work. The metro rail project is no exception," he continued. 

The second metro-rail route from Hemayetpur to Bhatara is another case in point. The MRT Line-5 (northern) project, which was approved on the same day that the MRT Line-1 got approval, is lagging further behind. 

The cost of the MRT Line-5 project is estimated at Tk41,238crore. 

The preliminary study and design for the line from Hemayetpur to Bhatara via Gabtoli, Mirpur 10, Kochukhet, Banani and Gulshan 2 is yet to be completed. 

DMTCL officials said a feasibility study for the project had been completed.  

The DMTCL proposed a new schedule for MRT Line-1 project which projected the commencement of work in depot areas by the beginning of next year and on the main line, including underground stations, by January 2023.

In the new schedule, the DMTCL is asking for a deadline extension to September 2021 for the final design of the MRT Line-1, which had been slated for completion in July 2020. This step is crucial because other preliminary work, such as contract packages, preparation of tender documents, and land acquisition depend on the final design. 

The capacity of the proposed MRT Line-1 is 34,740 passengers per hour per direction, which implies that the line will carry approximately 70,000 people from the airport to Kamalapur and vice versa every hour.

The completion of the project means access to transport across the city for 13.66 lakh citizens per day. The number is about 2.83 times higher than that of the ongoing MRT Line-6 project.

Bangladesh / Infograph / Top News

road / JICA / project / MRT

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Photo: Bloomberg
    India's Adani slammed by $48 bln stock rout, clouding record share sale
  • Infograph: TBS
    State banks spend 80% of their forex for govt imports in H1
  • Global central banks preaching on pay are enforcing squeeze too
    Global central banks preaching on pay are enforcing squeeze too

MOST VIEWED

  • No new roads before national election: Obaidul Quader
    No new roads before national election: Obaidul Quader
  • Photo: TBS
    Transport strike in Sylhet from Monday to demand release of Chhatra Dal leader
  • Metro Rail project will bridge the gap between time loss and economic development. Photo: Rajib Dhar
    Metro rail to be operational till 5pm on Sunday for Ijtema
  • File Photo
    GMP issues traffic directives to reduce sufferings of Ijtema devotees
  • WB considering aid to Dhaka-Ctg high-speed train, 4 more projects
    WB considering aid to Dhaka-Ctg high-speed train, 4 more projects
  • One step closer to relocation of Dhaka bus terminals
    One step closer to relocation of Dhaka bus terminals

Related News

  • PM to unveil 25 dev projects in Rajshahi on Sunday
  • More than 50% Japan-funded projects lagging behind
  • Brac Bank gets $100m green finance facility from Jica, Citi NA
  • Hundreds take their first metro rides as Tk2.74 lakh earned in fare on first day
  • Japanese tech to raise Dhaka airport's ground handling capacity

Features

Sketch:TBS

Why we need consumer education for consumer wellbeing

8h | Thoughts
Dr Ahsan H Mansur, Executive Director, Policy Research Institute. Illustration: TBS

Twin shocks call for stronger domestic policy response

9h | Thoughts
December-er shohor, taxi taken for airport and the Park Street bathed in lights. Photo: Jannatul Naym Pieal

Exploring Kolkata on foot, empowered by Google Maps

10h | Explorer
Island hopping in Bangladesh?

Island hopping in Bangladesh?

12h | Panorama

More Videos from TBS

Kajol’s road paintings bring change in Gafargaon

Kajol’s road paintings bring change in Gafargaon

1d | TBS Stories
Carew & Company witnessed a remarkable growth

Carew & Company witnessed a remarkable growth

1d | TBS Stories
After all the controversies, how is Shah Rukh Khan's ‘Pathaan’?

After all the controversies, how is Shah Rukh Khan's ‘Pathaan’?

1h | TBS Entertainment
PCB recalls cricketers from BPL ahead of PSL

PCB recalls cricketers from BPL ahead of PSL

1d | TBS SPORTS

Most Read

1
Picture: Collected
Bangladesh

US Embassy condemns recent incidents of visa fraud

2
Four top bankers arrested in DSA case filed by S Alam group 
Bangladesh

Four top bankers arrested in DSA case filed by S Alam group 

3
Illustration: TBS
Banking

16 banks at risk of capital shortfall if top 3 borrowers default

4
Photo: Collected
Splash

Hansal Mehta responds as Twitter user calls him 'shameless' for making Faraaz

5
A frozen Beyond Burger plant-based patty. Photographer: AKIRA for Bloomberg Businessweek
Bloomberg Special

Fake meat was supposed to save the world. It became just another fad

6
Representational Image
Banking

Cash-strapped Islami, Al-Arafah and National turn to Sonali Bank for costly fund

EMAIL US
[email protected]
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Privacy Policy
  • Comment Policy
Copyright © 2023
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - [email protected]

For advertisement- [email protected]