Work on 294 piles of Padma Bridge completed
Skip to main content
  • Home
  • Economy
    • Aviation
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • World+Biz
  • Sports
  • Features
    • Book Review
    • Brands
    • Earth
    • Explorer
    • Fact Check
    • Family
    • Food
    • Game Reviews
    • Good Practices
    • Habitat
    • Humour
    • In Focus
    • Luxury
    • Mode
    • Panorama
    • Pursuit
    • Wealth
    • Wellbeing
    • Wheels
  • Epaper
  • More
    • Subscribe
    • Videos
    • Thoughts
    • Splash
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • COVID-19
    • Games
    • Long Read
    • Interviews
    • Offbeat
    • Podcast
    • Quiz
    • Tech
    • Trial By Trivia
    • Magazine
  • বাংলা
The Business Standard

Thursday
March 30, 2023

Sign In
Subscribe
  • Home
  • Economy
    • Aviation
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • World+Biz
  • Sports
  • Features
    • Book Review
    • Brands
    • Earth
    • Explorer
    • Fact Check
    • Family
    • Food
    • Game Reviews
    • Good Practices
    • Habitat
    • Humour
    • In Focus
    • Luxury
    • Mode
    • Panorama
    • Pursuit
    • Wealth
    • Wellbeing
    • Wheels
  • Epaper
  • More
    • Subscribe
    • Videos
    • Thoughts
    • Splash
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • COVID-19
    • Games
    • Long Read
    • Interviews
    • Offbeat
    • Podcast
    • Quiz
    • Tech
    • Trial By Trivia
    • Magazine
  • বাংলা
THURSDAY, MARCH 30, 2023
Work on 294 piles of Padma Bridge completed

Bangladesh

UNB
15 July, 2019, 12:30 pm
Last modified: 15 July, 2019, 12:48 pm

Related News

  • Construction of railway track on Padma Bridge completed
  • Trial run on Padma Bridge railway on 4 April
  • Test run of special train on Mawa-Bhanga section next week
  • Shariatpur transport sector booms in 7 months since Padma Bridge opening
  • How are the Shimulia ghat businesses faring after Padma bridge?

Work on 294 piles of Padma Bridge completed

Most challenging task is over, say engineers

UNB
15 July, 2019, 12:30 pm
Last modified: 15 July, 2019, 12:48 pm
Work on 294 piles of Padma Bridge completed

Work on the last pile among 294 of the long-awaited Padma Bridge has been completed.

Engineers started the piling work on the number seven pile at 11:35am and finished it after eight hours at 8:20pm at the 26thNo pier of the bridge.

"It's a matter of great joy that the most challenging task is over on completion of this work," said Executive Engineer (Main bridge )  Dewan Mohammad Abudul Quader.

"It's a real victory against the mighty Padma River and its rough nature," he said.

Engineer Dewan said the last piling work on the bottom section was completed on Wednesday and the top section's tube was put on Thursday.

Later, incessant rains interrupted the welding work which took two more days.

The pile driving started on Sunday after theNon-Destructive Testing(NDT)and it is done now, he added.

The 120-metre long and 3-metre width pile was made with China-made steel plate at Mawa Construction Yard.

The pile was driven into the the riverbed where 1.40 lakh cubic metres of water flows per second.

Earlier, engineers had faced complications due to soft ground soil at the Mawa point in Munshiganj. The work was then shifted to Jazira point in Shariatpur district.

"That was really a challenging job to finalise the design of the piers for that complications. But lastly the work is done," engineer Dewan said.

Padma Multiporpuse Bridge authorities said the construction of all the piers is expected to be completed within this year while the span installation work will continue.

An engineer told UNB that China Major Bridge Engineering Construction Company was given a deadline till July 31 for the piling work but they have completed the work two weeks ahead of the schedule.

The main bridge will be on 41 spans to be installed on 42 piers. The total 42 piers will be placed on 294 piles.

Meanwhile, the 14th span was installed on June 29 making 2,100 metres of the 6.15-kmlong mega structure visible. The '3-C' span was set up on pillars 15 and 16.

Work on the country's largest bridge started in December 2015. The structure started becoming visible with the installation of 150-metre span on pillars 37 and 38 on October 30, 2017.
 

Top News

Padma Bridge

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Photo: BSS
    Non-resident doctors not getting allowance for 9 months
  • Unemployment drops to 3.6% on increased women's participation
    Unemployment drops to 3.6% on increased women's participation
  • Photo: Collected
    Now Prothom Alo editor sued under DSA

MOST VIEWED

  • Photo: Bangladesh Railway Fans' Forum
    Bus-train collides at capital's Khilgaon on Monday night
  • Photo: Collected from Facebook
    Arav Khan under UAE police 'surveillance'
  • Sehri, Iftar timings this year
    Sehri, Iftar timings this year
  • Representational image
    Airport Road traffic to be restricted on Fridays from 31 March
  • World praises Bangladesh on Independence Day
    World praises Bangladesh on Independence Day
  • Body found in missing car owned by Rooppur power plant's MD
    Body found in missing car owned by Rooppur power plant's MD

Related News

  • Construction of railway track on Padma Bridge completed
  • Trial run on Padma Bridge railway on 4 April
  • Test run of special train on Mawa-Bhanga section next week
  • Shariatpur transport sector booms in 7 months since Padma Bridge opening
  • How are the Shimulia ghat businesses faring after Padma bridge?

Features

Kishoreganj produces around 1,500 metric tons of dried fish yearly. Of this, more than 800 metric tons are produced in Kuliarchar Das Para Dangi. Photo: Noor-A-Alam

A fishing village by Kalni river: The charm and economics of Das Para Shutki Dangi

1h | Panorama
Masum Billah, Journalist, Sketch: TBS

Where are we with the Myanmar case at the ICJ?

42m | Panorama
Sketch: TBS

Policymakers keep solving the wrong banking problem

22m | Panorama
If Gandhi is such an asset for the BJP, why has he just been thrown out of India’s Parliament? Photo: Reuters

Modi's Rahul playbook is a tale of unchecked populism

22h | Panorama

More Videos from TBS

Messi in 100 goal club for the national team

Messi in 100 goal club for the national team

14h | TBS SPORTS
Teams can pick starting XIs after toss

Teams can pick starting XIs after toss

11h | TBS SPORTS
Sunglasses are for TK 150-300 only

Sunglasses are for TK 150-300 only

15h | TBS Stories
Shahida Begum: Best farmer of Faridpur

Shahida Begum: Best farmer of Faridpur

17h | TBS Stories

Most Read

1
Sadeka Begum. Photo: Courtesy
Panorama

Sadeka's magic lamp: How a garment worker became an RMG CEO

2
Photo: Bangladesh Railway Fans' Forum
Bangladesh

Bus-train collides at capital's Khilgaon on Monday night

3
Photo illustration: Steph Davidson; Getty Images
Bloomberg Special

Elon Musk's global empire has made him a burning problem for Washington

4
Photo: Collected from Facebook
Bangladesh

Arav Khan under UAE police 'surveillance'

5
Sabila Nur attempts to silence critics with university transcripts
Splash

Sabila Nur attempts to silence critics with university transcripts

6
Sehri, Iftar timings this year
Bangladesh

Sehri, Iftar timings this year

EMAIL US
[email protected]
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Privacy Policy
  • Comment Policy
Copyright © 2023
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - [email protected]

For advertisement- [email protected]