Metro rail’s construction progressing fast with 49.15% completion
Skip to main content
  • Home
  • Economy
    • Aviation
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • World+Biz
  • Sports
  • Features
    • Book Review
    • Brands
    • Earth
    • Explorer
    • Fact Check
    • Family
    • Food
    • Game Reviews
    • Good Practices
    • Habitat
    • Humour
    • In Focus
    • Luxury
    • Mode
    • Panorama
    • Pursuit
    • Wealth
    • Wellbeing
    • Wheels
  • Epaper
  • More
    • Subscribe
    • Videos
    • Thoughts
    • Splash
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • COVID-19
    • Games
    • Long Read
    • Interviews
    • Offbeat
    • Podcast
    • Quiz
    • Tech
    • Trial By Trivia
    • Magazine
  • বাংলা
The Business Standard

Friday
March 31, 2023

Sign In
Subscribe
  • Home
  • Economy
    • Aviation
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • World+Biz
  • Sports
  • Features
    • Book Review
    • Brands
    • Earth
    • Explorer
    • Fact Check
    • Family
    • Food
    • Game Reviews
    • Good Practices
    • Habitat
    • Humour
    • In Focus
    • Luxury
    • Mode
    • Panorama
    • Pursuit
    • Wealth
    • Wellbeing
    • Wheels
  • Epaper
  • More
    • Subscribe
    • Videos
    • Thoughts
    • Splash
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • COVID-19
    • Games
    • Long Read
    • Interviews
    • Offbeat
    • Podcast
    • Quiz
    • Tech
    • Trial By Trivia
    • Magazine
  • বাংলা
FRIDAY, MARCH 31, 2023
Metro rail’s construction progressing fast with 49.15% completion

Infrastructure

BSS
04 September, 2020, 05:00 pm
Last modified: 04 September, 2020, 05:08 pm

Related News

  • Metro Rail's Shewrapara and Uttara South stations open to public
  • Govt urged for loans on easy terms to facilitate home construction
  • WB pledges $150mn to Dhaka North for metro station-based transport corridors
  • Four more Metro Rail coaches reach Mongla port
  • Metro rail to run at full capacity on Uttara-Agargaon route from July

Metro rail’s construction progressing fast with 49.15% completion

Rail tracks are being set up from Diabari to Mirpur section where electric lines are also being installed

BSS
04 September, 2020, 05:00 pm
Last modified: 04 September, 2020, 05:08 pm
File Photo: Mumit M
File Photo: Mumit M

The construction work of the country's first ever metro rail is progressing in full swing maintaining health guidelines amid Covid-19 pandemic with completion of its overall 49.15 percent construction, an official said.

"Workers, technicians, engineers and other concerned are working 'day-night' to complete the construction work of the metro rail from Uttara to Motijheel as its overall 49.15 percent construction has been accomplished," Managing Director of Dhaka Mass Transit Company Limited (DMTCL) MAN Siddique told BSS today.

The overall physical progress of the first phase construction of the metro rail from Uttara to Agargaon is 75.50 percent, he said, adding the construction progress of the second phase from Agargaon to Motijheel stood at 42.50 percent.

He said at present, 10.86-kilometre viaduct out of 11.73-kilometer metro rail between Uttara and Agargaon has become visible. "The construction work of MRT Line-6 in the city under the Fast Track project is going on in full swing," he added.

Siddique hoped that if the current pace of work continues by following safety rules during the ongoing coronavirus situation, the rail project might be completed within December 2022.

According to the project details, rail coaches have been built in Japan to ply Line-6 track from Diabari of Uttara to Motijheel in city as coaches are waiting for shipment and the shipment will start as soon as the corona situation improves.

Rail tracks are being set up from Diabari to Mirpur section where electric lines are also being installed, it said.

It also said there will have a total of 16 stations on the 21-km route of the Mass Rapid Transit (MRT) Line-6 and the digital devices will be used in all stations.

The stations include Uttara North, Uttara Center, Uttara South, Pallabi, Mirpur-11, Mirpur-10, Kazipara, Shewrapara, Agargaon, Bijoy Sarawni, Farmgate, Karwan Bazar, Shahbag, Dhaka University, Bangladesh Secretariat and Motijheel.

"If everything goes normal, people of the city will be able to travel from Diabari to Motijheel by the dream metro rail before the stipulated time," Siddique said.

He said work is underway to install rail tracks and power lines in Mirpur part. "The areas where viaduct is installed, the rail tracks and power lines are also being set up there," he went on saying.

While visiting the metro rail project site, labourers are seen working persistently. At the same time, construction of the stations and installation of railway tracks are in progress. In Mirpur-Motijheel section, viaduct is being installed by large cranes; on which the rail tracks will be laid.

Technicians and workers said they are following health guidelines to avert the coronavirus infection while working "24 hours a day" to complete the project timely.

The metro rail project is being constructed at the cost of T219.85 billion, of which, Japan's aid agency JICA will provide Tk165 billion.

Bangladesh / Top News

Metro Rail / construction / progressing / completion

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Picture: Collected
    After UFS scam, ICB forms task force to monitor asset managers' activities
  • Why these 3 new platforms are performing poorly on bourses
    Why these 3 new platforms are performing poorly on bourses
  • Photo: Collected
    Metro Rail's Shewrapara and Uttara South stations open to public

MOST VIEWED

  • Photo: TBS
    Construction of railway track on Padma Bridge completed
  • Chinese EZ set to develop fast with new developer onboard
    Chinese EZ set to develop fast with new developer onboard
  • Photo: Mumit M/TBS
    Payra port ready for large ships after dredging at Rabnabad channel
  • Dhaka Metro Rail. Photo: Rajib Dhar
    City planners against metro rail in Chattogram
  • The construction of Patenga Container Terminal is almost complete and the authorities hope vessels can anchor here by June. The terminal is expected to handle four lakh of containers and oil tankers. The photo was recently taken from Patenga. Photo: Mohammad Minhaz Uddin
    Framework signed with Saudi Arabia's RSGT for Patenga Container Terminal concession
  • Matarbari Power Plant. File Photo: BSS
    Matarbari access road work begins in July

Related News

  • Metro Rail's Shewrapara and Uttara South stations open to public
  • Govt urged for loans on easy terms to facilitate home construction
  • WB pledges $150mn to Dhaka North for metro station-based transport corridors
  • Four more Metro Rail coaches reach Mongla port
  • Metro rail to run at full capacity on Uttara-Agargaon route from July

Features

The exterior of the Crown RS Advance is sleek and modern, with a long body, sharp lines and an aggressive front grille. Photo: Akif Hamid

The Toyota Crown RS Advance: The luxury sedan for car enthusiasts

2h | Wheels
Illustration: TBS

'If local investors think the regulatory framework is uncertain, foreigners would doubly think so'

1h | Panorama
Illustration: TBS

A year on, the country's first transgender UP chairman serves people with humility

2h | Panorama
Paradise Kingfisher. Photo: John Cornforth

Into the world of avian tail feathers

1d | Earth

More Videos from TBS

Pakistan's matches in the World Cup could take place in Bangladesh

Pakistan's matches in the World Cup could take place in Bangladesh

12h | TBS SPORTS
Putin launches nuclear drills with Yars missile

Putin launches nuclear drills with Yars missile

15h | TBS World
Hritika's dream, transgenders will establish by studying

Hritika's dream, transgenders will establish by studying

2h | TBS Stories
People are waiting to cross the Padma Bridge by train

People are waiting to cross the Padma Bridge by train

17h | TBS Stories

Most Read

1
Nusrat Ananna and Nafis Ul Haque Sifat. Illustration: TBS
Pursuit

The road to MIT and Caltech: Bangladeshi undergrads beat the odds

2
Sadeka Begum. Photo: Courtesy
Panorama

Sadeka's magic lamp: How a garment worker became an RMG CEO

3
Photo: Bangladesh Railway Fans' Forum
Bangladesh

Bus-train collides at capital's Khilgaon on Monday night

4
Photo: Wikimedia Commons
Tech

Microsoft-owned Github fires entire Indian engineering team

5
Representational image
Bangladesh

Airport Road traffic to be restricted on Fridays from 31 March

6
Photo: Texas A&M
Science

Massive asteroid expected to pass by Earth this weekend

EMAIL US
[email protected]
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Privacy Policy
  • Comment Policy
Copyright © 2023
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - [email protected]

For advertisement- [email protected]