Poor allocation in transmission may overshadow power generation glory
Skip to main content
  • Home
  • Economy
  • Stocks
  • Analysis
  • World+Biz
  • Sports
  • Features
  • Epaper
  • More
    • Subscribe
    • COVID-19
    • Bangladesh
    • Splash
    • Videos
    • Games
    • Long Read
    • Infograph
    • Interviews
    • Offbeat
    • Thoughts
    • Podcast
    • Quiz
    • Tech
    • Archive
    • Trial By Trivia
    • Magazine
    • Supplement
  • বাংলা
The Business Standard

Thursday
July 07, 2022

Sign In
Subscribe
  • Home
  • Economy
  • Stocks
  • Analysis
  • World+Biz
  • Sports
  • Features
  • Epaper
  • More
    • Subscribe
    • COVID-19
    • Bangladesh
    • Splash
    • Videos
    • Games
    • Long Read
    • Infograph
    • Interviews
    • Offbeat
    • Thoughts
    • Podcast
    • Quiz
    • Tech
    • Archive
    • Trial By Trivia
    • Magazine
    • Supplement
  • বাংলা
THURSDAY, JULY 07, 2022
Poor allocation in transmission may overshadow power generation glory

Energy

Saifuddin Saif & Eyamin Sajid
29 March, 2022, 10:40 pm
Last modified: 31 March, 2022, 03:42 pm

Related News

  • Energy ministry to recommend reduced working hours, work-from-home to save electricity
  • PM seeks people’s cooperation as govt forced to execute load-shedding
  • FBCCI for uninterrupted power supply in industry
  • PM urges countrymen not to illuminate buildings, markets to save electricity
  • Load shedding, power crisis will not last long: State minister

Poor allocation in transmission may overshadow power generation glory

Saifuddin Saif & Eyamin Sajid
29 March, 2022, 10:40 pm
Last modified: 31 March, 2022, 03:42 pm
Poor allocation in transmission may overshadow power generation glory
Infographic: TBS

With surplus electricity causing Bangladesh to make capacity payments for idle plants, the government apparently keeps on spending more and more on power generation, rather than focusing on transmission and distribution to end users.

Two big power projects have eaten into more than 54% of the budget pie in the revised Annual Development Programme (ADP) for FY22, while 85 others in the power and energy sector remain underfunded, which could lead to an additional delay in implementation, according to a Programming Division analysis of the sector's multi-year public investment programme.

The total revised ADP allocation for FY22 amounted to Tk39,214 crore.

The analysis report said the RADP allocations for 85 projects were lower than expected on the basis of the expenditure profiles for these projects, implying that the projects are relatively underfunded for the fiscal 2021-22.

"This increased negative fiscal space is mainly caused by the inclusion of the Rooppur Power Plant Project with a total cost of Tk1,13,000 crore and a total increase of the Matarbari Ultra Super Critical coal fired Power Project from Tk35,984 crore to Tk51,855 crore," it adds.

The report says the budget ceiling for the power and energy sector for the ADP 2022-23 and beyond needs to increase by more than 10% to accommodate the Rooppur Plant and the cost increase of the Matarbari power project.

Otherwise it will most likely negatively impact project implementation of the whole sector, the report said.

To shed light on an underfunded transmission project, take for example the Barapukuria-Bogura-Kaliakoir 400kV Transmission Line Project that was taken up in January 2019 to ensure quality power supply to the country's northern region.

The project, with around 12% physical progress as of December last year, saw a 18% cut in budget allocation in the RADP, which might further delay its implementation. 

Project Director Sk Zakiruzzaman told The Business Standard, "If we get allocation on time as per needs, we will be able to complete it within the extended timeframe of 2024." 

In another example, the replacement of Ashuganj Old 132 kV AIS Substation by New 132 kV GIS Substation Project experienced its cost trimmed by 90% in the revised ADP.

The project's objective is to modernise Ashuganj Old Substation to reduce the chance of national grid failure and ensure reliable power supply to Dhaka as well as Ashuganj and its neighbouring areas.

The project, which started in April 2018, has made only 25% progress. The remaining work needs to be done by December 2022.

The report suggests project implementation delays can, to some extent, be avoided when projects that are near completion receive sufficient allocation.

From a financial perspective, 19 projects in the power and energy sector could be completed in FY23 if 6% of the total sector budget is allocated to these projects.

The RADP 2021-22 includes 89 ongoing projects for the Power and Energy Sector, of which six are new projects. Among 89 projects, 79 belong to the power sub-sector and 10 to the Energy sub-sector.

Fund deficit to continue in 2022-25

The ongoing projects will not receive sufficient allocation for their implementation within FY22-FY25.

The required budget for the ongoing projects for these years is higher than the project budget ceiling. For FY23, Tk43,135 crore has been projected for the sector against the actual demand of Tk73,478 crore. Similarly, in FY24, the fund deficit amounts to Tk30,514 crore. And, in FY25, there will be a surplus fund of TkTk23,497 crore, according to the Programming Division's analysis.

Nine power projects with higher allocation

A total of 9 projects, 10% of total projects, in the power sub sector have received a higher budget allocation for FY22 than the fiscal budget estimate for FY22 suggested in RADP 2020-21.

The projects are construction of Ashuganj  400MW combined cycle power plant , Payra thermal power plant, Matarbari coal-fired power plant,  power evacuation facilities of Rooppur Power plant, 1.5 million consumer connection in rural area, construction of new substation under DPDC, 5 lakh pre-payment metre installation and technical assistance for power sector development project.

The Programming Division said this indicates that if all the other implementation factors and conditions do not change, these projects will be expedited vis-à-vis their current implementation trajectory.

Although the analysis indicates an improvement of implementation for these projects, all of these projects are expected to be delayed against the DPP (development projects proposal) completion date, according to the Programming Division.

There are four projects for which implementation will be earlier or as indicated in the DPPs of these projects. These are construction of 100MW solar power plant at Madarganj in Jamalpur, Matarbari coal power, land acquisition of Bangladesh Singapore 700MW coal power and Bheramara combined cycle power plant project.

Lack of transmission line leads to unused capacity

Around 70% capacity of the Payra 1320MW Thermal Power Plant, the largest power plant of the country, has remained idle since December 2020 due to a lack of required transmission line.

Construction of Patuakhali (Payra)-Gopalganj-Mawa-Aminbazar 400kV Transmission Line was supposed to be ready in line with the power plant.

However, the power plant came into production, but the transmission line is yet to be completed.

The transmission line – being built by the Power Grid Company of Bangladesh (PGCB) – is now half done. The line requires seven towers across the River Padma to connect Dhaka.

Golam Kibria, managing director of Power Grid Company, told TBS that the Padma Bridge authorities were tasked with constructing the transmission towers across the River Padma.

"But due to priority on building the bridge, the Padma Bridge authorities delayed the transmission line and had recently started constructing the electric towers in the River," he said.

Golam Kibria said, "Work on the towers is in progress. Two out of seven towers have already been installed. Padma Bridge authorities assured us that the remaining five will be constructed by the middle of this year."

But electric cable connection on either side of the river will take another five-six months after the completion of the towers, he added.
Power Evacuation Facilities of Rooppur Nuclear Power Plant has become another cause of worry for the Power Division and the Power Development Board of Bangladesh.

The first unit of the power plant is expected to be operational by 2024, but the power evacuation infrastructure facilities have very little progress.

As of December last year, the physical progress of the project is only 25%, though the lines are expected to be prepared by December 2023.

Infrastructure Development for Power Evacuation Facilities of Rooppur Nuclear Power Plant is being implemented by line of credit finance at cost of Tk10,981.74 crore.

Project Director QM Safiqul Islam, however, does not see underbudget an issue over the timely implementation of the project.

He said, "Finding qualified contractors and cost hike of construction materials seem to be the reasons behind a provable delay in the project completion."

Experts said it will be a massive loss for keeping the 2,400MW plant's capacity idle due to a lack of transmission lines.

Energy expert Professor Dr Mohammad Tamim, said, "Payra power plant was supposed to give us a big relief from expensive liquid fuel. The plant can help us shut some expensive oil-based power plants. But we cannot take the opportunity to use the least cost option due to a lack of transmission lines," he said.

The losses for keeping capacity idle  can double if the Rooppur and Rampal power plants come into operation without having adequate transmission lines, he added.

"If there is now any single most important project that is nothing other than setting up the power evacuation line from Rampal to Dhaka," said Prof Dr M Tamim.

Project delay increases losses

Due to the delays in implementing the power transmission projects, the Bangladesh Power Development Board has been incurring losses as it gives capacity charge to the power plant owners as a penalty for keeping unused capacity standby. 

In the fiscal 2020-2021, the losses of BPDB increased to Tk11,287.46 crore, which was Tk4,000 crore in FY11. 

To keep the losing entity operational, on the other hand, the government is pouring subsidies into the sector. The subsidies of the government for the BPDB have significantly also increased.  

In FY11, the subsidy in the power sector was Tk4,511.90 crore, which reached Tk11,777.91 crore in FY21. 

Installation of Single Point Mooring causes fund crisis in energy sub sector

There are 10 ongoing projects in the energy subsector. The negative fiscal space in the energy subsector is primarily caused by a large project - the Installation of Single Point Mooring project.

There is another project "Installation of wellhead compressor at location of Titas Gas field" that has received a higher allocation than expected on the basis of expenditure profiles. 

All the other projects in the energy sub sector have received a lower budget allocation in RADP for FY22 than expected on the basis of the expenditure profiles. These lower allocations seem to indicate that one could expect a total implementation delay of about 0.5 to 3.5 years per project against the DPP completion date, says the analysis of the Programming Division.

Bangladesh / Top News

Power Generation / Electricity

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Photo: MumitM/TBS
    Energy ministry to recommend reduced working hours, work-from-home to save electricity
  • Passenger dies after helper pushes him off bus following scuffle over fare
    Passenger dies after helper pushes him off bus following scuffle over fare
  • FILE PHOTO: British Prime Minister Boris Johnson leaves 10 Downing Street in London, Britain, February 9, 2022. REUTERS/Tom Nicholson
    Scandal-ridden Boris Johnson to quit as UK prime minister

MOST VIEWED

  • Photo: MumitM/TBS
    Energy ministry to recommend reduced working hours, work-from-home to save electricity
  • File Photo: State Minister for Power, Energy and Mineral Resources Nasrul Hamid/UNB
    Nasrul Hamid hints at fuel price hike amid global crisis 
  • BPC looks for $2b as fuel stock depletes fast
    BPC looks for $2b as fuel stock depletes fast
  • Transmitting Electricity: Workers install an electricity transmission tower at Srinagar in Munshiganj. The Power Division took up a project of 400kV Double circuit transmission lines from Patuakhali (Payra) to Aminbazar (Dhaka) with a deadline of December 2020 for transmitting electricity from the Payra power plant, but Power Grid Company of Bangladesh failed to complete it due to difficulties in line building in the River Padma. Photo: Mumit M
    PM seeks people’s support to cut power subsidy amid hard times
  • File photo
    PM urges countrymen not to illuminate buildings, markets to save electricity
  • Area-wise load shedding schedule will be announced: PM
    Area-wise load shedding schedule will be announced: PM

Related News

  • Energy ministry to recommend reduced working hours, work-from-home to save electricity
  • PM seeks people’s cooperation as govt forced to execute load-shedding
  • FBCCI for uninterrupted power supply in industry
  • PM urges countrymen not to illuminate buildings, markets to save electricity
  • Load shedding, power crisis will not last long: State minister

Features

Farsim is keen on listening to what his clients really want; in this profession attention is key. Photo: Noor-A-Alam

Making it as an audio engineer

5h | Pursuit
Illustration: TBS

Applystart: Helping students navigate the maze of foreign university applications

6h | Pursuit
The sea beach in Kuakata. Photo: Syed Mehedy Hasan

Five places in Southern Bangladesh you could visit via Padma Bridge

1d | Explorer
Genex Infosys Limited is the country's largest call centre with more than 2,000 seats and full-set equipment. Photo: Courtesy

How domestic demand made Genex Infosys a BPO industry leader

1d | Panorama

More Videos from TBS

Load shedding is back

Load shedding is back

6h | Videos
Photo: TBS

Has Russia gained anything in its invasion of Ukraine?

7h | Videos
Behind the story of 'Aske Amar Mon Bhalo Nei'

Behind the story of 'Aske Amar Mon Bhalo Nei'

19h | Videos
Is Donbas Putin’s next target?

Is Donbas Putin’s next target?

22h | Videos

Most Read

1
Photo: Collected
Africa

Uganda discovers gold deposits worth 12 trillion USD

2
TBS Illustration
Education

Universities may launch online classes again after Eid

3
Area-wise load shedding schedule will be announced: PM
Bangladesh

Area-wise load shedding schedule will be announced: PM

4
Padma Bridge opens up investment spree in south
Industry

Padma Bridge opens up investment spree in south

5
Build Dhaka East-West Elevated Expressway, relocate kitchen markets: PM
Bangladesh

Build Dhaka East-West Elevated Expressway, relocate kitchen markets: PM

6
File Photo: BSS
Energy

India pulls out of LoC funding for part of Rooppur power transmission work

EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Privacy Policy
  • Comment Policy
Copyright © 2022
The Business Standard All rights reserved
Technical Partner: RSI Lab
BENEATH THE SURFACE
A boat sails through the River Meghna carrying rice bran, a popular cattle feed, from a rice mill in Ashuganj to cattle markets. There are around 250 rice mills in Ashuganj that produce rice bran. The photo was taken recently. Photo: Rajib Dhar

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net